Waypoint Development · Construction Ops

Oak Hill · Tyler

TOH · HUD 113-36092 · Berkadia 109464736 · 221(d)(4) · 6450 Oak Hill Blvd, Tyler, TX 75703 · 240 units · Nations Construction · Cross Architects · mortgage $40,272,100 @ 5.95% · IE 2026-06-24 · SC 2028-07-24

Sat Nov 7, 2026 Data compiled Saturday, November 7, 2026 · 9:08 AM CT
Live page clock: America/Chicago
Actual progress
12.0%
Funded basis: HUD-approved Draw 4 (funded 10/9). Source pkg Nations Pay App #4 (in Draw 5) shows 15.3% — not HUD-approved
Scheduled
4.0%
Funded basis: Draw 4 pkg. Pay App #4 HUD-5372 shows 7% for Oct — not HUD-approved
Last funded draw
#4 · $1.45M
$1,450,019.25 · HUD-approved · funded 10/9/26 · UPB $7,848,775.46
Draw #5
Submitted 11/2
$999,139.21 · Berkadia targeting Mon 11/9 · held for $3,208.50 mechanic’s lien on title · not approved or funded
Draws · Draw 4 HUD-approved & funded 10/9/2026 · Draw 5 submitted to Berkadia 11/2 (Nations Pay App #4 → borrower Draw 5)

Draw 5 submitted · funding held for title lien

Draw 05 · Draw 5 package (submitted) · Pay App #4 executed · Draw 4 funding package

Action required

Urgent issues

HUD-92448 · Contractor’s Requisition (funded basis: Pay App #3 → Draw 4, HUD-approved & funded 10/9) · source pkg Pay App #4 (Draw 5, submitted 11/2) shown below

% Complete by trade

12.0%
Actual vs scheduled 4.0% (HUD-approved Draw 4)
HUD-92449 not found — chart from HUD-92448 Amounts Complete ÷ Cost Breakdown (Pay App #3 / Master Form 9/30). Approved/funded 10/9: actual 12.0% / scheduled 4.0% per Berkadia funding pkg.
Site Utilities
82.9%
Earth Work
74.1%
Concrete
37.6%
Plumbing and Hot Water
18.8%
General Requirements
12.0%

Source: Nations Pay App #3 HUD-92448 (work through 2026-09-25) + Master Form borrower copy 9/30 — Subtotal complete $3,663,205 / Cost Breakdown $30,671,472 = 11.94%. Net this requisition $1,388,595 after 10% retainage. Pay App #3 · Master Form. Other trades $0 complete (not charted).

Bars = funded basis (Draw 4, HUD-approved 10/9). Source package, not HUD-approved: Nations Pay App #4 (work through 10/27, executed 10/29; in Draw 5, submitted to Berkadia 11/2) — Site Utilities 96.6% · Earth Work 85.3% · Concrete 54.1% · Plumbing 27.7% · General Requirements 16.0% · Electrical 4.2% · Lawns & Planting 3.8%; subtotal $4,706,091 / $30,671,472 = 15.3%; HUD-5372 Oct actual 15% / scheduled 7%. Cross Site Visit 4 (10/27): ~15% complete, work in compliance with CDs. Headline stays 12.0% / 4.0% until Draw 5 is HUD-approved (HUD-92449 / approved 92403 not found).

Field

Photos / field reports

BuildPunch 2026-11-06 photo 1BuildPunch 2026-11-06 photo 2BuildPunch 2026-11-06 photo 3BuildPunch 2026-11-06 photo 4BuildPunch 2026-11-06 photo 5BuildPunch 2026-11-06 photo 6BuildPunch 2026-11-06 photo 7BuildPunch 2026-11-06 photo 8BuildPunch 2026-11-04 photo 1BuildPunch 2026-11-04 photo 2BuildPunch 2026-11-04 photo 3BuildPunch 2026-11-04 photo 4

Strip: BuildPunch Daily Report 2026-11-06 (8 photos taken 11/5–11/6 — cloudy, site muddy; stakes pinned around paving area; adjustments made for concrete pours on pads and paving; crew ECS 1, concrete 6, electrical 1, plumbing 1, utilities 2) first; then 2026-11-04 (4 photos — partly cloudy; mud delay, site too muddy to work). Older strips (10/30, 10/29) dropped. Not staged: report labeled 11/3 but sent 11/2 evening (10 photos: Bldg 5 PT cables, Bldg 7 awaiting concrete, paving forms, Bldg 7 plumbing and electrical underground) and the 11/3 rain-out (3) — both filed by Ada. No 11/5 report in mail. ECS this week: FR 38 Bldg 8 slab 280 CY 3500 psi in compliance + pour #1 PT pre-pour OK; FR 36R pavement density passed; FR 39 Bldg 2 PT elongation NC (see urgent). Break reports 15–20 (11/6), 7-day: Bldg 6 (cast 10/29) 3120 / 3730 / 3860 psi, Bldg 8 (cast 10/30) 3610 / 3320 / 3070 psi; no LOW flags; 28-day tests 11/26–11/27.

Live rebuild from Drive + Gmail + Ada filing · Sat Nov 7, 2026

Submittal log

Table rebuilt 2026-11-07: 10/31 log (52), no new numbers. #26.1 Insulation Rev1 returned 11/2 (Cross could not review garbled pages). No dispositions on #38, #12.1; #5.2 Eaton revision and #37 resubmittal not received; no response on #36. Statuses only with evidence. Private tracker: tylersubmittals.waypointdevelopment.com.

#DescriptionStatusDate
#26.1Insulation - Rev1
Nations resubmitted 10/24; Cross 11/2: cannot review — multiple pages with garbled text (PDF conversion); Shane getting supplier to reissue. Ada filed 10/26, tracked 11/2
Returned2026-11-02
#38Floor & Roof Trusses
Nations 10/30 for review; Ada filed 10/30; no disposition as of 11/7
Open2026-10-30
#37Pool Design (Cross Revise & Resubmit)
Nations 10/24; Cross 10/26 REVISE AND RESUBMIT — sub must fill out NET Public Health forms (spec book, LP02). Ada filed both PDFs 10/26 · resubmittal not received as of 11/7
Returned2026-10-26
#12.1Appliances - Rev1
Nations resubmitted 10/24 (PDF dated 10.23.26); Cross 10/28 looped in Arturo Banales; no disposition as of 11/7. Ada filed 10/26
Open2026-10-24
#5.2Meter Gear - Rev2
AOS review 10/14: incomplete — only “CH” & “Maint” panels. Call 10/23: panel count below drawings; Eaton to correct counts + add specs, revised submittal expected week of 10/26 — not received as of 11/7
Returned2026-10-14
#36Paving Cement Slurry
Nations 10/6 — flagged urgent for civil engineer review; Ada filed 10/6 (Drive PDF)
Open2026-10-06
#2.2Concrete Mix Design - Rev2
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — OMIT changed to Alt supplier
Open2026-08-03
#5.1Meter Gear - Rev1
Ada-filed Rev1 PDF on Drive; no architect disposition found this refresh
Open—
#6.2Cabinet Shop Drawings - Rev2 - Club Only
Ada-filed Club Cabinet Shops Rev1 on Drive; no architect disposition found this refresh
Open—
#8Lighting
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — no comments date
Open—
#14Unit Doors & Trim
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — no comments date
Open—
#19Plumbing - Fixtures
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — no comments date
Open—
#20.1Hardware - Amenities & Units Rev1
Ada filed Rev1 PDF 9/28; Pay App #3 log sent 9/28 — no architect disposition yet
Open2026-09-28
#33Flooring
Drive PDF filed Ada 10/1 (recovered from email); Pay App #3 log blank disposition; samples still pending per Ada 10/1 tracker note
Open2026-09-09
#34Cabinet Finishes
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — no comments date
Open—
#35Pool Selections
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — no comments date
Open—
#10.1Misc Site Metals - Rev1 (Architect Review)
Cross 10/13: revise & resubmit awning (side drainage); other items color on site. DS stamp (ndouglas 10/12): revise & resubmit — “fence components not per DS.” Ada filed review PDF 10/20
Returned2026-10-13
#29.1Carports - Rev1
Nations 10/12; Cross returned same day — Rev1 changed all carports to 8′-2″, only van-accessible needs it. Ada filed submittal PDF 10/12; Cross markup not on Drive
Returned2026-10-12
#2Concrete Mix Design
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Revise and Resubmit
Returned2026-07-14
#2.1Concrete Mix Design - Rev1
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Revise and Resubmit
Returned2026-07-28
#3PT Shop Drawings
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Revise and Resubmit
Returned2026-07-17
#4Rebar Shop Drawings
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Revise and Resubmit
Returned2026-07-17
#5Meter Gear
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Revise and Resubmit
Returned2026-07-30
#6Cabinet Shop Drawings
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Revise and Resubmit
Returned2026-09-04
#7Windows
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Revise and Resubmit
Returned2026-07-27
#10Misc Site Metals
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Revise and Resubmit
Returned2026-07-28
#12Appliances
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Revise and Resubmit
Returned2026-09-09
#13Amenities Doors & Trim
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Revise and Resubmit
Returned2026-09-11
#20Hardware - Amenities & Units
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Revise and Resubmit
Returned2026-09-11
#26Insulation
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Revise and Resubmit
Returned2026-09-10
#29Carports
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Revise and Resubmit · superseded by #29.1 (10/12)
Returned2026-08-03
#31Floor Trusses
Drive Cross Reviewed PDF: architect stamp REVISE & RESUBMIT (AMBlackman 9.23.2026) — overrides Pay App #3 log “Reviewed as Noted”; SEOR corridor slope note 9/21 · new #38 Floor & Roof Trusses submitted 10/30
Returned2026-09-23
#4.1Rebar Shop Drawings - Rev1
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Reviewed as Noted
Reviewed2026-08-17
#6.1Cabinet Shop Drawings - Rev1
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Reviewed as Noted
Reviewed2026-09-11
#7.1Windows - Rev1
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Reviewed as Noted
Reviewed2026-09-18
#9Shower Doors & Mirrors
Pay App #3 log Reviewed as Noted 9/11; resubmit clubhouse mirrors still required (Ada filed review PDF 9/13)
Reviewed2026-09-11
#16Lightweight & Gypcrete
Cross-reviewed PDF on Drive (Ada filed 9/16); Max T-bar preference confirmed per prior owner thread
Reviewed2026-09-15
#18Roofing
Pay App #3 log Reviewed as Noted 9/17; finish options need physical samples + final selection
Reviewed2026-09-17
#22Rough Framing Materials
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Approved as Noted
Reviewed2026-07-27
#23Electrical Materials
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Reviewed as Noted
Reviewed2026-07-28
#24HVAC
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Reviewed as Noted
Reviewed2026-08-17
#25Masonry Materials
Pay App #3 log Reviewed as Noted 9/17; finish options + on-site samples still needed per Cross/Ada
Reviewed2026-09-17
#27Structural Steel
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Reviewed as Noted
Reviewed2026-08-10
#28Stairs & Railings
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Approved as Noted
Reviewed2026-08-05
#30Concrete Mix Design - Alt Supplier
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Reviewed as Noted
Reviewed2026-08-10
#32Roof Trusses
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Reviewed as Noted
Reviewed2026-09-22
#1Utilities - Materials & Vaults
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Approved
Approved2026-07-13
#3.1PT Shop Drawings - Rev1
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Approved
Approved2026-08-10
#11Retaining Wall
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Approved
Approved2026-07-30
#15Pool Equipment
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Approved
Approved2026-07-28
#17Plumbing - Materials
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Approved
Approved2026-07-20
#21Drywall Materials
Nations Pay App #3 log (in Draw 4 pkg, dated ~9/29) — Approved
Approved2026-07-27